Crozer Keystone Clinical Lab Consolidation
Project
Status :
Bids are due to John McManus by 4pm Wednesday 8/11/10.
MPE Contractors - Prebid Meeting/Walk-thru 10am 8/3/10. Meet in the main lobby
All trades Union
Roofing spec to follow - check MPE dwgs for openings.
Misc metals - patch roof openings - supports at rooftop units
Crozer Non-Critical IT Room Renovations
Project
Status :
Bids are due to John McManus by 4pm 8/18/10.
MPE Contractors - Prebid Meeting/Walk-tru 9am 8/3/10 - Meet in the main lobby.
Specificaitons will be available and posted on or about 8/3/10.
Franklin Towne Charter School
Project
Status :
Prevailing Wages
Bids due to John McManus by 2pm 8/11/10.
New school - 82000 sf with alternate for new gymnasium - 1800 sf
Sitework, building demolition of existing one story masonry retail bldg, 22000sf, curbs, paving, storm sewar, sanitary, chainlink fence, decorative fence, unit pavers, concrete plank, concrete, masonry, structural & misc. metals, carpentry, metal wall panels, wp, vapor barrier, weather barrier, hm, wood doors, coiling doors, curtain wall, translucent panels, drywall, ceramic, vct, carpet, resilient athletic flooring, wood stage flooring, chalk & tack, signage, toilet accessories, food service equipment, window treatments, manufactured casework, telescpoing stands, traction elevator.
*Note - Unit pricing for sitework
-Atlernates
Prototype
Project
Status :
Private
Riddle MOB Corridor Updates
Project
Status :
Private
We have been awarded this job.
Bids are due to Mike McManus 3pm June 9, 2010
St Mary Medical Center Hybrid OR Suite Expansion
Project
Status :
Private
Bids are due to John McManus by noon Thursday 7/29/10.
All trades - union
See spec 012300 for alternates
MPE contractors - select list
Phasing required - 5 phases - see phasing drawings
Questions must be received no later than noon Tuesday 7/20/10.
Walk through Friday 7/9/10 9am in the lobby of the St Clare Medial Building at St Mary Medical Center. Attendance is mandatory for MEP sub contractors.
St Mary Medical Center MS1D 3 Patient Rooms
Project
Status :
We are expecting award of this contract soon.
All sub bids due to John McManus by noon July 15, 2010
Specifications posted. Note the following discrepancies:
· Section 09310-10 Ceramic Tile Par. 3.5 & 3.6 ‘Joint Widths’ incorrectly calls for tile joint widths to be installed at 1/4”; the correct joint width is 1/8”.
· Sanded grout should be used; please submit samples.
St. Mary Medical Center Corridor Expansion
Project
Status :
Private
We are expecting award of this project soon.
Addendum #4 is posted. Re-price is due by 2pm 6/15/10.
Note in Addendum 4 the C drawings are in the MEP drawing file.
Prefer submissions via email. All trades are union. note plumbing, HVAC, sprinklers & electric are separate prime contracts.
Please review alternates - section 012300 - prior to doing takeoffs.
Job description - Small building addition with related sitework & paving.
Sitework, landscaping, irrigation system - note site specs are in sections 31 & 31.
Concrete foundations, structural steel, metal deck, roofing, vegitative roofing, spary fireproofing, metal panels, fluid applied vapor barrier, EIFS, doors, frames, hardware, dryall, studs, scoustic, VCT, vinyl base paint, wall protection, FEC
Job starts June 2010
|